Biomass Power Plant

CPW carried out Engineering, Procurement and Construction (EPC) work for Yanmar Rice Husk Gasification Project. Prior to EPC work, CPW performed Preliminary Study, Soil Boring & Testing, Site Survey, Soil Investigation and site preparation for the project. The project duration is 10 months.

 

Main Contractor : Chiyoda System Technology
Sub-Contractor : Chiyoda & Public Works Co., Ltd.
End User : Myanmar Agribusiness Public Corporation  (MAPCO)
Capacity of Rice husk : 1 ton/hour
Capacity of Generating Electricity : 5MW
Scope of work : Engineering, Procurement & Construction
Project Period : Oct 2016 ~ Jul 2017