CPW carried out Engineering, Procurement and Construction (EPC) work for Yanmar Rice Husk Gasification Project. Prior to EPC work, CPW performed Preliminary Study, Soil Boring & Testing, Site Survey, Soil Investigation and site preparation for the project. The project duration is 10 months.
Main Contractor : | Chiyoda System Technology |
Sub-Contractor : | Chiyoda & Public Works Co., Ltd. |
End User : | Myanmar Agribusiness Public Corporation (MAPCO) |
Capacity of Rice husk : | 1 ton/hour |
Capacity of Generating Electricity : | 5MW |
Scope of work : | Engineering, Procurement & Construction |
Project Period : | Oct 2016 ~ Jul 2017 |